Package EX10 – Hanoi – Hai Phong Expressway
VIDIFI DUYEN HAI INVESTMENT JOINT STOCK COMPANY
| 1. Project | Traffic Construction Project |
| 2. Total Invesment | 142.563.960.000 VND |
| 3. Scale | Construction of highway foundation: dredging, K90 black sand backfilling, geotextile reinforcement, sand cushioning for drainage, load filling, subgrade construction of mountain soil K98, 40cm of upper foundation, backfilling of soil margins stick K90, plant taluy roof grass
Construction of intersections and road 356: excavation and removal of soil KTH, K90 black sand backfill, reinforced geotextiles, drainage sand cushion, load filling, K95 black sand subgrade, K98 black sand subgrade, 35cm distribution lower foundation crushed stone, 20cm upper foundation crushed stone, 1kg/m2 permeable plastic watering; construction of 12cm plastic treatment base layer, 02 layers of concrete bottom layer 7cm thick; 01 layer of concrete with thickness of 5cm, construction of curbs, sidewalks and drainage system Construction of 4.8km of concrete embankments to protect the roofs of highways and highways |
| 4. About the complexity and construction conditions | Construction in favorable conditions in terms of the technical solutions of the appropriate design documents, reasonable construction methods. |
| 5. Other characteristics | According to common usage. |